Testimonials > Precast Concrete Electrical Shelters

Electrical Shelters, Union Bridge Modernization Project
Randy Newton, Manager of Construction Engineering, Kvaerner Process

"We have contracted Smith-Midland to design, fabricate, and install three Pre-Cast Concrete single story electrical buildings for Lehigh Portland Cement for the Union Bridge Modernization Project. When these 30’-0 wide buildings arrived on site it took less than one-week for each to be erected. These buildings ranged from 60’-0 to 100’-0 in length. The cost and time advantage over conventional masonry was exceptional. The Turnkey method provided the Project with a timely and cost effective solution to our Electrical Room building construction.

The fast track design/build solution placed the first Electrical Room erected on site within twelve weeks after placement of order."

View the actual letter